11611 W CALIFA ST 1-2 91601
Certificate Information: 11611 W CALIFA ST 1-2 91601
- Application / Permit
- 21016-20000-47030
- Plan Check / Job No.
- B21VN14643
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) 3-CAR GARAGE AND 9'-2" x 5'-11" PORTION OF (E) CARPORT INTO NEW UNIT (BULDING IS NOW A DUPLEX); REMOVE REMAINING 20'-9" X 11'-8" IRREGULAR SHAPED PORTION OF CARPORT
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Corrected on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | SELLA BENYAMIN |
| Corrections Issued | 11/23/2021 | SELLA BENYAMIN |
| Quality Review Completed | 11/24/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Plan Check Approved | 7/14/2022 | SELLA BENYAMIN |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 9/22/2023 | JACK KARGODORIAN |
| CofO Issued-Status Void | 7/31/2024 | RUBEN SALAS |
| Permit Finaled-Status Void | 7/31/2024 | RUBEN SALAS |
| Re-Activate Permit | 10/28/2024 | RUBEN SALAS |
| CofO Corrected | 10/28/2024 | RUBEN SALAS |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2022 | CARLOS AGUILERA |
| Permit | Cleared | 1/21/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 5/19/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/29/2022 | Not Ready for Inspection | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 1/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Light Gage Steel Frame | 1/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 1/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 2/7/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/10/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/7/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/7/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 4/7/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 4/7/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 4/7/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 4/7/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/20/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 4/20/2023 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/1/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Steel/Welding | 5/1/2023 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 5/1/2023 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 5/1/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 5/3/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/12/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/12/2023 | Partial Approval | JACK KARGODORIAN |
| Gas Test | 6/14/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 6/14/2023 | Approved | JACK KARGODORIAN |
| Sewer | 6/14/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/25/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/25/2023 | Approved | JACK KARGODORIAN |
| Final | 8/25/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 8/25/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 8/25/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 8/25/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 8/25/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/1/2023 | Approved | JACK KARGODORIAN |
| Final | 9/1/2023 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 9/1/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/1/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Final | 9/21/2023 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | JACK KARGODORIAN |