8604 N GLENCREST DR 91352

Certificate Information: 8604 N GLENCREST DR 91352

Application / Permit
21016-20000-46515
Plan Check / Job No.
B21VN14593
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 12/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 10/29/2021 SELLA BENYAMIN
Corrections Issued 11/2/2021 SELLA BENYAMIN
Issued 12/9/2021 APPLICANT
Building Plans Picked Up 7/28/2022 APPLICANT
CofO in Progress 11/16/2023 DAVID ANDERSON
Permit Finaled 12/28/2023 RUBEN SALAS
CofO Issued 12/28/2023 RUBEN SALAS
Permit Finaled 12/28/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/2/2021 CARLOS AGUILERA
Sewer availability Cleared 11/2/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 12/9/2021 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/15/2021 Partial Inspection WILLIAM KUEHN
Footing/Foundation/Slab 1/13/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/19/2022 Corrections Issued JOHN HAYES
Green Building Rough 1/19/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/25/2022 Corrections Issued MATTHEW NELSON
Green Building Rough 1/25/2022 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 2/25/2022 Corrections Issued DAVID MATSON
Green Building Rough 2/25/2022 Not Ready for Inspection DAVID MATSON
Special/Order Compliance 8/16/2022 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 8/23/2023 Not Ready for Inspection DAVID ANDERSON
Final 8/23/2023 Not Ready for Inspection DAVID ANDERSON
Green Building Final 8/23/2023 Corrections Issued DAVID ANDERSON
Green Building Rough 8/23/2023 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 8/23/2023 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 9/26/2023 Partial Approval DAVID ANDERSON
Final 9/26/2023 Not Ready for Inspection DAVID ANDERSON
Green Building Final 9/26/2023 Approved DAVID ANDERSON
Green Building Rough 9/26/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 9/26/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/14/2023 Approved DAVID ANDERSON
Final 11/14/2023 OK to Issue CofO DAVID ANDERSON
PLUMBING-Final 11/14/2023 Approved DAVID ANDERSON