14907 W DEVONSHIRE ST 91345
Certificate Information: 14907 W DEVONSHIRE ST 91345
- Application / Permit
- 21016-20000-43415
- Plan Check / Job No.
- B21VN14355
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- Issued on 11/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/24/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 11/8/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 11/18/2021 | APPLICANT |
| Plan Check Approved | 11/23/2021 | ALDO UBAU |
| Issued | 11/23/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/28/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C93095 | 19535 NORDHOFF ST APT # 457 NORTHRIDGE, CA 91324 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/17/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 2/17/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/17/2022 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 2/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 2/17/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 3/17/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Wood Frame | 3/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/23/2022 | Approved Pending GreenApproval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/23/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/23/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 3/29/2022 | No Access for Inspection | JENNIFER RABUCHIN |
| Insulation | 3/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 4/14/2022 | Partial Approval | MICHEL ABAJAN |
| Drywall Nailing | 8/11/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/11/2022 | Corrections Issued | JENNIFER RABUCHIN |