23860 W BURBANK BLVD 91367
Certificate Information: 23860 W BURBANK BLVD 91367
- Application / Permit
- 21016-20000-42454
- Plan Check / Job No.
- B21VN14268
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL, REMOVE WALLS AROUND KITCHEN AND INSTALL BEAMS, NEW SLIDING DOORS AND KITCHEN REMODEL TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/6/2022
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2021 | SERGIO MUNIZ |
| Corrections Issued | 10/25/2021 | SERGIO MUNIZ |
| Plan Check Approved | 11/23/2021 | SERGIO MUNIZ |
| Issued | 11/24/2021 | APPLICANT |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Permit Finaled | 9/2/2022 | TROY SANDERS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/3/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2021 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 12/15/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/12/2022 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 1/12/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/19/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 1/19/2022 | Approved | TROY SANDERS |
| Insulation | 1/19/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/19/2022 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 1/19/2022 | Partial Inspection | JESUS PINEDA |
| Grading Pre-Inspection | 7/22/2022 | Not Ready for Inspection | TROY SANDERS |
| Final | 9/2/2022 | Permit Finaled | TROY SANDERS |
| Gas Test | 9/2/2022 | Approved | TROY SANDERS |
| Grading Pre-Inspection | 9/2/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/2/2022 | Approved | TROY SANDERS |