7010-7010 1/2 N AMIGO AVE 91335

Certificate Information: 7010-7010 1/2 N AMIGO AVE 91335

Application / Permit
21016-20000-42158
Plan Check / Job No.
B21VN14245
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*ePlan Check* CONVERT (E) ATTACHED 2-CAR GARAGE IN THE (E) 1-STORY SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 1/25/2022
Issuing Office
Current Status
CofO Issued on 5/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 DANIEL YIP
Corrections Issued 10/22/2021 DANIEL YIP
Applicant returned to address corrections 1/19/2022 DANIEL YIP
Plan Check Approved 1/20/2022 DANIEL YIP
Issued 1/25/2022 APPLICANT
CofO in Progress 5/24/2023 SEAN WIRCH
Permit Finaled 5/24/2023 JOHN JANSON
CofO Issued 5/24/2023 JOHN JANSON
Permit Finaled 5/24/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/26/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/26/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/27/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor American Goal Construction Inc; Lic. No.: 632978-B 18375 VENTRUA BLVD #26      TARZANA, CA 91356

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/14/2022 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 2/22/2022 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 2/22/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/14/2022 Partial Approval VINCENT HANLEY
Green Building Final 3/14/2022 Approved VINCENT HANLEY
Insulation 3/14/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/14/2022 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 3/14/2022 Approved VINCENT HANLEY
Sewer 3/14/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/16/2022 Approved VINCENT HANLEY
Drywall Nailing 3/16/2022 Approved VINCENT HANLEY
Green Building Rough 3/16/2022 Approved VINCENT HANLEY
HVAC-Rough 3/16/2022 Approved VINCENT HANLEY
Final 5/17/2022 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/17/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/17/2022 Approved VINCENT HANLEY
Final 6/15/2022 Not Ready for Inspection VINCENT HANLEY
Final 7/7/2022 Corrections Issued VINCENT HANLEY
Final 9/12/2022 Partial Inspection VINCENT HANLEY
Final 10/6/2022 Not Ready for Inspection VINCENT HANLEY
Service/Power Release 10/6/2022 Approved VINCENT HANLEY
Final 5/25/2023 OK to Issue CofO SEAN WIRCH