673 S MCCADDEN PL 90005

Certificate Information: 673 S MCCADDEN PL 90005

Application / Permit
21016-20000-42151
Plan Check / Job No.
B21VN14243
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 18' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/4/2022
Issuing Office
Current Status
CofO Issued on 9/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 JEFFREY TANGONAN
Corrections Issued 10/23/2021 JEFFREY TANGONAN
Issued 2/4/2022 APPLICANT
Building Plans Picked Up 2/4/2022 APPLICANT
CofO in Progress 8/24/2022 STUART CHAPMAN
Permit Finaled 9/16/2022 DEROLD HAUFF
CofO Issued 9/16/2022 DEROLD HAUFF
Permit Finaled 9/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/2/2021 WALLIE JONG
Sewer availability Cleared 11/2/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/3/2021 WALLIE JONG
HPOZ Cleared 1/13/2022 SUKI GERSHENHORN
Specific Plan Cleared 1/22/2022 ADRINEH MELKONIAN
Construction near power lines Cleared 1/28/2022 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/30/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/15/2022 Approved JUSTIN CURTIS
HVAC-Rough 4/15/2022 Approved JUSTIN CURTIS
PLUMBING-Rough 4/15/2022 Approved JUSTIN CURTIS
Insulation 4/21/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/25/2022 Approved ARTHUR SARGSYAN
Green Building Rough 4/25/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 4/25/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 5/3/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/5/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/18/2022 Approved STUART CHAPMAN
Sewer 5/18/2022 Approved FREDDIE RIVERA
Shower Pan 5/18/2022 Approved STUART CHAPMAN
Underground Mechanical 5/18/2022 Partial Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Not Ready ADAM ESCOTO
Final 8/17/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/17/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 8/17/2022 Approved ALIZAH MAYAGOITIA
Final 8/22/2022 Corrections Issued STUART CHAPMAN
Green Building Final 8/22/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 8/24/2022 Approved STUART CHAPMAN
Final 8/24/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/24/2022 Approved STUART CHAPMAN
PLUMBING-Final 8/24/2022 Approved STUART CHAPMAN
Service/Power Release 8/24/2022 Approved STUART CHAPMAN