1467 N FAIRBANKS PL 90026
Certificate Information: 1467 N FAIRBANKS PL 90026
- Application / Permit
- 21016-20000-42105
- Plan Check / Job No.
- B21VN14214
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-2" X 27'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER DESIGN.
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/22/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/16/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 2/2/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| Issued | 3/1/2022 | APPLICANT |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/16/2021 | MANUEL TEJADA |
| Tract Map conditions | Cleared | 11/17/2021 | DANIEL CORONADO |
| Address approval | Cleared | 11/19/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 11/19/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | STEVE MELGAR |
| City Hist. Cultural Monument | Cleared | 12/7/2021 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 12/7/2021 | LAMBERT GIESSINGER |
| Tenant Habitability Plan | Cleared | 1/21/2022 | PHILLIP MUNGUIA |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | N E Construction; Lic. No.: 696948-B | 22817 VENTURA BLVD #930 WOODLAND HILLS, CA 91364 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/21/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/28/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/28/2022 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 6/5/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/5/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/10/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 7/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/10/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 7/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 7/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/28/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 7/28/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 7/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 8/24/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/27/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 12/19/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 1/10/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 1/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 1/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/10/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 1/31/2025 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 1/31/2025 | Approved | OSVALDO PARAMO |
| Final | 2/3/2025 | Conditional Approval | OSVALDO PARAMO |
| Service/Power Release | 2/3/2025 | Approved | OSVALDO PARAMO |