20730-20732 W GAULT ST 91306
Certificate Information: 20730-20732 W GAULT ST 91306
- Application / Permit
- 21016-20000-41258
- Plan Check / Job No.
- B21VN14141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. CONVERT (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). COMPLY WITH DEPARTMENT ORDER effective date 12/10/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 5/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2021 | KEVIN MORALES |
| Corrections Issued | 10/20/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 12/31/2021 | KEVIN MORALES |
| Plan Check Approved | 4/19/2022 | KEVIN MORALES |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 4/24/2025 | ALEXANDER HANDY |
| Permit Finaled | 5/28/2025 | JOHN JANSON |
| CofO Issued | 5/28/2025 | JOHN JANSON |
| Permit Finaled | 5/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 10/26/2021 | MIGUEL GAMBOA |
| Address approval | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 4/13/2022 | RIDWAN HARDY |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/8/2024 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/31/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 3/6/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/22/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/22/2024 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 4/22/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/8/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 5/8/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 5/8/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 5/8/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 5/8/2024 | Approved | ALEXANDER HANDY |
| Sewer | 5/8/2024 | Approved | ALEXANDER HANDY |
| Insulation | 6/24/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/10/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/7/2024 | Approved | GEVORK IPCHYAN |
| Final | 3/11/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/11/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/8/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 4/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Final | 4/8/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 4/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 4/23/2025 | Approved | ALEXANDER HANDY |
| Final | 4/23/2025 | OK to Issue CofO | ALEXANDER HANDY |
| PLUMBING-Final | 4/23/2025 | Approved | ALEXANDER HANDY |