18144 W NAPA ST 91325

Certificate Information: 18144 W NAPA ST 91325

Application / Permit
21016-20000-41256
Plan Check / Job No.
B21VN14140
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO (N) A.D.U. PER STATE LAW "COMPLY WITH DEPARTMENT ORDER effective date 01/27/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 8/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2021 APPLICANT
Assigned to Plan Check Engineer 10/18/2021 CARLOS MONTES
Corrections Issued 10/19/2021 CARLOS MONTES
Applicant returned to address corrections 11/11/2021 CARLOS MONTES
Applicant returned to address corrections 12/3/2021 CARLOS MONTES
Applicant returned to address corrections 12/7/2021 CARLOS MONTES
Plan Check Approved 3/1/2022 CARLOS MONTES
Issued 3/22/2022 APPLICANT
CofO in Progress 8/15/2023 DAVID SCANTLIN
Permit Finaled 8/16/2023 DANIEL ORRANTE
CofO Issued 8/16/2023 DANIEL ORRANTE
Permit Finaled 8/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/29/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 10/29/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/29/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/29/2021 ROSE MARIE SMITH
Construction near power lines Cleared 2/24/2022 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/23/2022 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 8/23/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 8/23/2022 Corrections Issued JEFFREY PARD
Underground Mechanical 8/25/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 9/2/2022 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 9/13/2022 Corrections Issued JEFFREY PARD
Deputy Drilled-In Anchors 9/15/2022 Approved SEAN WIRCH
Excavation/Setback/Form/Re-Bar 9/20/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/14/2022 Partial Approval JOHN KIDWELL
Underground Mechanical 10/14/2022 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 10/24/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 10/24/2022 Partial Approval DAVID SCANTLIN
Underground Mechanical 10/24/2022 Not Ready for Inspection DAVID SCANTLIN
Sewer 11/1/2022 Approved JOHN KIDWELL
Underground Mechanical 11/1/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 11/7/2022 Approved DAVID SCANTLIN
Insulation 11/10/2022 Approved JOHN KIDWELL
Drywall Nailing 11/18/2022 Approved KRISTEN CAUSEY
Shower Pan 1/23/2023 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 1/30/2023 Approved MORRIS JACKSON
Shower Pan 1/30/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/21/2023 No Access for Inspection HENRY KIM
Final 6/26/2023 Corrections Issued JOHN KIDWELL
Green Building Final 6/26/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 6/26/2023 Approved JOHN KIDWELL
Green Building Final 7/5/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved JOHN KIDWELL
Green Building Final 7/7/2023 Not Ready for Inspection JOHN KIDWELL
Final 8/14/2023 OK to Issue CofO DAVID SCANTLIN
Green Building Final 8/14/2023 Approved DAVID SCANTLIN