8813-8815 N RINCON AVE 91352

Certificate Information: 8813-8815 N RINCON AVE 91352

Application / Permit
21016-20000-40088
Plan Check / Job No.
B21VN14063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Conversion of existing 492 s.f. 2-car garage to ADU. Per Ordinance 186481
Permit Issued
Issued on 12/28/2021
Issuing Office
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 HERNAN ARREOLA
Corrections Issued 10/21/2021 HERNAN ARREOLA
Plan Check Approved 12/19/2021 HERNAN ARREOLA
Issued 12/28/2021 APPLICANT
CofO in Progress 6/5/2023 MATTHEW NELSON
Permit Finaled 6/8/2023 MICHAEL SMITH
CofO Issued 6/8/2023 MICHAEL SMITH
Permit Finaled 6/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/25/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/25/2021 LEE GUILBEAUX
Sewer availability Cleared 10/25/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/25/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/22/2022 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 3/2/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 3/4/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 3/17/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Rough 3/17/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/15/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/2/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/18/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/18/2022 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Rough 7/18/2022 Not Ready for Inspection DEANDRE HOFFMAN
HVAC-Rough 7/18/2022 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Rough 7/18/2022 Approved DEANDRE HOFFMAN
Insulation 8/26/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 9/9/2022 Partial Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/9/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 9/14/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/14/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/3/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 10/3/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/14/2023 Approved MATTHEW NELSON
Final 4/14/2023 Corrections Issued MATTHEW NELSON
Green Building Final 4/14/2023 Corrections Issued MATTHEW NELSON
Green Building Rough 4/14/2023 Approved MATTHEW NELSON
MERV13>=Final 4/14/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 4/14/2023 Approved MATTHEW NELSON
Final 6/2/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 6/2/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved MATTHEW NELSON