14652 W HORTENSE ST 91403
Certificate Information: 14652 W HORTENSE ST 91403
- Application / Permit
- 21016-20000-39733
- Plan Check / Job No.
- B21VN14037
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20 ' X 28' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/8/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 11/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Applicant returned to address corrections | 8/2/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 8/9/2022 | RAPHAEL ROSAS |
| Issued | 6/10/2024 | APPLICANT |
| CofO in Progress | 5/5/2026 | RAUL OLAGI |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/17/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2021 | DAGOVERTO GUERRERO |
| ZI | Cleared | 12/15/2021 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 1/6/2022 | BRIAN MILLER |
| Construction near power lines | Cleared | 3/12/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Melkonyan Artsvik; Lic. No.: 1016658-B | 921 E CEDAR AVE BURBANK, CA 91501 |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/11/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 7/18/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/22/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/9/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/10/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/10/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/19/2024 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/19/2024 | No Access for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/19/2024 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/19/2024 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/31/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/31/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/31/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 12/31/2024 | Approved | ARAM AVEDISIAN |
| Wood Frame | 12/31/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/10/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/4/2025 | Approved | JACK KARGODORIAN |
| Insulation | 3/26/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/26/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 4/2/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 6/4/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/26/2025 | Approved | LOUIS ESCOTO |
| Service/Power Release | 1/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 1/27/2026 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/4/2026 | Corrections Issued | MISAEL ESPARZA |
| Final | 2/4/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/4/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 2/4/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 2/4/2026 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 2/4/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 2/4/2026 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/13/2026 | Corrections Issued | MISAEL ESPARZA |
| Final | 2/13/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 2/13/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 2/13/2026 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 2/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 2/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/18/2026 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/18/2026 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 4/2/2026 | Approved | RAUL OLAGI |
| Green Building Final | 4/2/2026 | Approved | RAUL OLAGI |
| HVAC-Final | 4/2/2026 | Approved | RAUL OLAGI |
| PLUMBING-Final | 4/2/2026 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 4/2/2026 | Approved | RAUL OLAGI |
| Final | 4/3/2026 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 4/9/2026 | Corrections Issued | MISAEL ESPARZA |
| Final | 4/22/2026 | Partial Inspection | MISAEL ESPARZA |
| Final | 4/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/1/2026 | OK to Issue CofO | MISAEL ESPARZA |