6715-6723 W BEVERLY BLVD 90036
Certificate Information: 6715-6723 W BEVERLY BLVD 90036
- Application / Permit
- 21016-20000-39699
- Plan Check / Job No.
- B21VN14036
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT LOBBY PORTION OF THE (E) DUPLEX TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C). ALL WORK PER ENGINEERING. ADU Address is 6723 Beverly Blvd.
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | COLIN LOREDO |
| Corrections Issued | 11/16/2021 | COLIN LOREDO |
| Quality Review Completed | 11/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| Application Withdrawn | 4/15/2022 | COLIN LOREDO |
| Corrections Issued | 4/15/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 4/15/2022 | COLIN LOREDO |
| Plan Check Approved | 5/9/2022 | COLIN LOREDO |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 1/17/2025 | RONNIE MINDANAO |
| No Progress | 2/20/2025 | DEROLD HAUFF |
| CofO in Progress | 2/20/2025 | DEROLD HAUFF |
| CofO Issued | 2/21/2025 | DEROLD HAUFF |
| Permit Finaled | 2/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2021 | JEREMY CHOK |
| Address approval | Cleared | 12/3/2021 | JEREMY CHOK |
| Sewer availability | Cleared | 1/31/2022 | JEREMY CHOK |
| Abandoned oil well | Cleared | 3/19/2022 | DWIGHT SANKEY |
Contact Information
| Contractor | Mid Construction Group; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/8/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/18/2024 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/18/2024 | Partial Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/22/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/14/2024 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 8/14/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 8/14/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 8/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/20/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 8/29/2024 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 9/4/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/6/2024 | Conditional Approval | RONNIE MINDANAO |
| METHANE-Rough | 9/6/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 9/6/2024 | Conditional Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 9/17/2024 | Conditional Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/18/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 9/18/2024 | Conditional Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Approved | RONNIE MINDANAO |
| Insulation | 9/27/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 9/27/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/7/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/9/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 10/11/2024 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 10/21/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 10/30/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/1/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/6/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 12/6/2024 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 12/6/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 12/6/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 12/6/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/10/2024 | Approved | RONNIE MINDANAO |
| Service/Power Release | 12/10/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 12/11/2024 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 12/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Approved | RONNIE MINDANAO |
| Service/Power Release | 12/16/2024 | Approved | RONNIE MINDANAO |
| Final | 1/17/2025 | OK to Issue CofO | RONNIE MINDANAO |