6715-6723 W BEVERLY BLVD 90036

Certificate Information: 6715-6723 W BEVERLY BLVD 90036

Application / Permit
21016-20000-39699
Plan Check / Job No.
B21VN14036
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT LOBBY PORTION OF THE (E) DUPLEX TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C). ALL WORK PER ENGINEERING. ADU Address is 6723 Beverly Blvd.
Permit Issued
Issued on 8/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 COLIN LOREDO
Corrections Issued 11/16/2021 COLIN LOREDO
Quality Review Completed 11/16/2021 OMID HEDAYAT
Building Plans Picked Up 11/17/2021 APPLICANT
Application Withdrawn 4/15/2022 COLIN LOREDO
Corrections Issued 4/15/2022 COLIN LOREDO
Applicant returned to address corrections 4/15/2022 COLIN LOREDO
Plan Check Approved 5/9/2022 COLIN LOREDO
Issued 8/10/2022 APPLICANT
CofO in Progress 1/17/2025 RONNIE MINDANAO
No Progress 2/20/2025 DEROLD HAUFF
CofO in Progress 2/20/2025 DEROLD HAUFF
CofO Issued 2/21/2025 DEROLD HAUFF
Permit Finaled 2/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/29/2021 JEREMY CHOK
Address approval Cleared 12/3/2021 JEREMY CHOK
Sewer availability Cleared 1/31/2022 JEREMY CHOK
Abandoned oil well Cleared 3/19/2022 DWIGHT SANKEY

Contact Information

Contractor Mid Construction Group; Lic. No.: 1030925-B 5850 W 3RD STREET #160      LOS ANGELES, CA 90036

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/8/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 7/8/2024 Not Ready for Inspection RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 7/16/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 7/16/2024 Not Ready for Inspection RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 7/18/2024 Partial Approval RONNIE MINDANAO
Footing/Foundation/Slab 7/18/2024 Partial Approval RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 7/22/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 7/22/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 8/12/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Rough 8/14/2024 Corrections Issued RONNIE MINDANAO
HVAC-Rough 8/14/2024 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 8/14/2024 Approved RONNIE MINDANAO
Wood Frame 8/14/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 8/20/2024 Approved RONNIE MINDANAO
HVAC-Rough 8/29/2024 Corrections Issued RONNIE MINDANAO
HVAC-Rough 9/4/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 9/6/2024 Conditional Approval RONNIE MINDANAO
METHANE-Rough 9/6/2024 Approved RONNIE MINDANAO
Wood Frame 9/6/2024 Conditional Approval RONNIE MINDANAO
Deputy Wood Construction 9/17/2024 Conditional Approval RONNIE MINDANAO
BUILDING-Rough-Frame 9/18/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Not Ready for Inspection RONNIE MINDANAO
Insulation 9/18/2024 Conditional Approval RONNIE MINDANAO
BUILDING-Rough-Frame 9/27/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Approved RONNIE MINDANAO
Insulation 9/27/2024 Approved RONNIE MINDANAO
Wood Frame 9/27/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 10/7/2024 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 10/9/2024 Approved RONNIE MINDANAO
Drywall Nailing 10/11/2024 Corrections Issued ANTHONY RAMOS
Drywall Nailing 10/21/2024 Corrections Issued RONNIE MINDANAO
Drywall Nailing 10/30/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 11/1/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 12/6/2024 Corrections Issued RONNIE MINDANAO
Final 12/6/2024 Corrections Issued RONNIE MINDANAO
HVAC-Final 12/6/2024 Approved RONNIE MINDANAO
PLUMBING-Final 12/6/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 12/6/2024 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 12/6/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 12/10/2024 Approved RONNIE MINDANAO
Service/Power Release 12/10/2024 Not Ready for Inspection RONNIE MINDANAO
Final 12/11/2024 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 12/11/2024 SGSOV Not Ready RONNIE MINDANAO
Final 12/16/2024 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved RONNIE MINDANAO
Service/Power Release 12/16/2024 Approved RONNIE MINDANAO
Final 1/17/2025 OK to Issue CofO RONNIE MINDANAO