161 S NORMANDIE AVE #14 90004

Certificate Information: 161 S NORMANDIE AVE #14 90004

Application / Permit
21016-20000-38140
Plan Check / Job No.
B21VN13982
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) REC. ROOM INTO ACCESSORY DWELLING UNIT (402 SQ FT) PER GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 12/21/2021
Issuing Office
Valley
Current Status
CofO Corrected on 1/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 JEROME MAGAT PALMA
Corrections Issued 10/21/2021 JEROME MAGAT PALMA
Plan Check Approved 12/8/2021 JEROME MAGAT PALMA
Building Plans Picked Up 12/15/2021 APPLICANT
Issued 12/21/2021 APPLICANT
CofO in Progress 12/19/2022 JONATHAN QUACH
CofO Issued-Status Void 12/27/2022 ERNESTO CORRAL
Permit Finaled-Status Void 12/27/2022 ERNESTO CORRAL
Re-Activate Permit 1/17/2023 ERNESTO CORRAL
CofO Corrected 1/30/2023 ERNESTO CORRAL
Permit Finaled 1/30/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 11/23/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 11/23/2021 KHOUNG LE
Sewer availability Cleared 11/23/2021 KHOUNG LE

Contact Information

Contractor Schon Tepler Construction, Inc; Lic. No.: 969338-B 6250 HOLLYWOOOD BLVD 10M      LOS ANGELES, CA 90028

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/12/2022 Not Ready for Inspection JONATHAN QUACH
Wood Frame 7/12/2022 Not Ready for Inspection JONATHAN QUACH
Green Building Rough 7/14/2022 Not Ready for Inspection TED RIES
Wood Frame 7/14/2022 Not Ready for Inspection TED RIES
Green Building Rough 7/21/2022 Approved JONATHAN QUACH
Wood Frame 7/21/2022 Approved JONATHAN QUACH
Drywall Nailing 8/2/2022 Approved JONATHAN QUACH
Final 10/24/2022 Partial Inspection JONATHAN QUACH
Green Building Final 10/24/2022 Not Ready for Inspection JONATHAN QUACH
Smoke Detectors 10/24/2022 Approved JONATHAN QUACH
Final 11/8/2022 Not Ready for Inspection JONATHAN QUACH
Green Building Final 11/8/2022 Not Ready for Inspection JONATHAN QUACH
Final 12/19/2022 OK to Issue CofO JONATHAN QUACH
Green Building Final 12/19/2022 Approved JONATHAN QUACH