11723-11725 N MONOGRAM AVE 91344
Certificate Information: 11723-11725 N MONOGRAM AVE 91344
- Application / Permit
- 21016-20000-38131
- Plan Check / Job No.
- B21VN13981
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE AND 15'-6" X 10'-10" IRREG SHAPED PORTION OF SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT (631 SQ FT) PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 10/21/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/6/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Issued | 1/28/2022 | APPLICANT |
| CofO in Progress | 9/4/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/30/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 11/16/2021 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/31/2022 | Partial Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 5/22/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 7/23/2024 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 8/19/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/29/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 10/1/2024 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 11/1/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/14/2024 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 11/14/2024 | Not Ready for Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/16/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 12/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 1/3/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/3/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 1/3/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/14/2025 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/22/2025 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/22/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/28/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/28/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 1/28/2025 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 1/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/4/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 2/4/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/10/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 2/25/2025 | Approved | LOUIS ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/2/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Final | 7/2/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 7/2/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 7/2/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 7/2/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/2/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 7/7/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 7/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 7/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 7/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 8/4/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 8/13/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/25/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 8/25/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 8/25/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 9/3/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 9/3/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 9/4/2025 | Approved | CHRISTOPHER ROJAS |