1157 W 53RD ST 90037
Certificate Information: 1157 W 53RD ST 90037
- Application / Permit
- 21016-20000-38029
- Plan Check / Job No.
- B21VN13958
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage 331.99 square feet into new ADU. Also add onto garage 386.19 square feet. New total square feet 718.19 square feet.
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | JOE VO |
| Corrections Issued | 10/15/2021 | JOE VO |
| Applicant returned to address corrections | 10/29/2021 | JOE VO |
| Applicant returned to address corrections | 1/10/2022 | JOE VO |
| Plan Check Approved | 1/25/2022 | JOE VO |
| Issued | 1/28/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | SABAS ALONSO |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | KHOUNG LE |
| Sewer availability | Cleared | 12/10/2021 | KHOUNG LE |
| Construction near power lines | Cleared | 1/7/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Perez Construction; Lic. No.: 1016553-B | 1500 W 220TH ST TORRANCE, CA 90501 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 4/5/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/5/2022 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 5/11/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 6/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/1/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/14/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 6/14/2022 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 6/14/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/30/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/30/2022 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 6/30/2022 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 6/30/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/1/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/9/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/9/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 8/9/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/9/2022 | Approved | SABAS ALONSO |
| Insulation | 8/12/2022 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 8/24/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/12/2022 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 9/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 10/13/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 10/13/2022 | Approved | STUART CHAPMAN |
| Final | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 11/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/8/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 11/8/2022 | Approved | SABAS ALONSO |
| Final | 11/28/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/28/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 12/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/3/2023 | OK to Issue CofO | SABAS ALONSO |