2172 N BEVERLY GLEN BLVD 90077
Certificate Information: 2172 N BEVERLY GLEN BLVD 90077
- Application / Permit
- 21016-20000-37136
- Plan Check / Job No.
- B21VN13911
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) FIRST STORY GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). SEE COMMENTS.
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2021 | LUIS RINCON |
| Corrections Issued | 10/20/2021 | LUIS RINCON |
| Applicant returned to address corrections | 3/4/2022 | LUIS RINCON |
| Plan Check Approved | 3/30/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 3/16/2023 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
| CofO Issued | 3/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/23/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 3/30/2022 | LUIS RINCON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/9/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 5/24/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 6/1/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 6/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 8/2/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 8/18/2022 | Conditional Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 8/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 8/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/25/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 8/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/31/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 8/31/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 8/31/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 8/31/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 10/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 10/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 10/4/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 10/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 10/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 1/18/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 2/15/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/15/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 2/15/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 2/15/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/28/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| Final | 3/9/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 3/9/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |