16052 W DEVONSHIRE ST 91344

Certificate Information: 16052 W DEVONSHIRE ST 91344

Application / Permit
21016-20000-37105
Plan Check / Job No.
B21VN13891
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 MOHAMMAD ESMAILI
Corrections Issued 12/30/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 1/4/2022 APPLICANT
Applicant returned to address corrections 3/24/2022 MOHAMMAD ESMAILI
Plan Check Approved 5/12/2022 KHUONG TRUONG
Issued 5/12/2022 APPLICANT
CofO in Progress 1/6/2023 CHRISTOPHER DELLEFIELD
CofO Issued 2/6/2023 MICHAEL SMITH
Permit Finaled 2/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/21/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/21/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/25/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 5/9/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 6/14/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 6/14/2022 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 6/17/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 6/17/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/17/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/30/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 6/30/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/5/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/5/2022 Approved JAVIER RAMOS JR
HVAC-Rough 7/7/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/13/2022 Conditional Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 7/13/2022 Approved DEANDRE HOFFMAN
Insulation 7/19/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/22/2022 Approved JAVIER RAMOS JR
Drywall Nailing 7/22/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 7/22/2022 Approved JAVIER RAMOS JR
Green Building Rough 7/22/2022 Approved JAVIER RAMOS JR
Underground Mechanical 7/22/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/1/2022 Approved JAVIER RAMOS JR
Final 9/21/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/21/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/21/2022 Approved JAVIER RAMOS JR
Final 10/19/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 10/19/2022 Approved JAVIER RAMOS JR
Final 1/6/2023 OK to Issue CofO CHRISTOPHER DELLEFIELD