8059 N SHADYGLADE AVE 91605
Certificate Information: 8059 N SHADYGLADE AVE 91605
- Application / Permit
- 21016-20000-36926
- Plan Check / Job No.
- B21VN13856
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE AND 18' X 27' DETACHED STORAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). REMOVE (E) ATTACHED PORCH AT REAR. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/15/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/29/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| Plan Check Approved | 2/15/2022 | RAPHAEL ROSAS |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 11/27/2024 | MATTHEW NELSON |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2022 | ABHIMAN HENNADIGE |
| Construction near power lines | Cleared | 2/15/2022 | JOHN BACON |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | ABHIMAN HENNADIGE |
| Sewer availability | Cleared | 2/24/2022 | ABHIMAN HENNADIGE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/29/2024 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 6/18/2024 | Conditional Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/18/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/18/2024 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 6/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/8/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/8/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/8/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/8/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/11/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/11/2024 | Partial Approval | DAVID ANDERSON |
| Insulation | 7/15/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/18/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/18/2024 | Approved | MATTHEW NELSON |
| Final | 11/18/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 11/18/2024 | Approved | MATTHEW NELSON |
| Final | 11/22/2024 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Approved | MATTHEW NELSON |