6449 N MAMMOTH AVE 91401
Certificate Information: 6449 N MAMMOTH AVE 91401
- Application / Permit
- 21016-20000-36854
- Plan Check / Job No.
- B21VN13815
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20' x 23' IRR. SHAPE DETACHED GARAGE/LAUNDRY ROOM TO ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/11/2022
- Issuing Office
- Current Status
- CofO Issued on 7/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | JEFFREY TANGONAN |
| Corrections Issued | 10/16/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 2/10/2022 | JEFFREY TANGONAN |
| Issued | 2/11/2022 | APPLICANT |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| CofO in Progress | 7/7/2022 | RICHARD DOCKUS |
| Permit Finaled | 7/12/2022 | MICHAEL SMITH |
| CofO Issued | 7/12/2022 | MICHAEL SMITH |
| Permit Finaled | 7/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/19/2021 | MIGUEL GAMBOA |
| Address approval | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 1/22/2022 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 1/31/2022 | RICARDO BOHORQUEZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 5/4/2022 | Partial Inspection | MICHEL ABAJAN |
| Sewer | 5/6/2022 | Corrections Issued | RICHARD DOCKUS |
| Sewer | 5/9/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/23/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 5/23/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 5/23/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 5/23/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 5/25/2022 | Approved | RICHARD DOCKUS |
| Insulation | 5/27/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 5/27/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 6/1/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/1/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 6/1/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/28/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/28/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 6/28/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 6/28/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 6/28/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 6/28/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/28/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 7/5/2022 | Approved | RICHARD DOCKUS |
| Final | 7/5/2022 | OK to Issue CofO | RICHARD DOCKUS |
| HVAC-Final | 7/5/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 7/5/2022 | Approved | RICHARD DOCKUS |