4180 N NAGLE AVE 91423

Certificate Information: 4180 N NAGLE AVE 91423

Application / Permit
21016-20000-36510
Plan Check / Job No.
B21VN13768
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 322 SQFT DETACHED GARAGE TO ADU, PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 LUISANGEL VALENZUELA
Corrections Issued 10/18/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/19/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/8/2022 LUISANGEL VALENZUELA
Plan Check Approved 3/24/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 3/25/2022 APPLICANT
Issued 5/4/2022 APPLICANT
CofO in Progress 12/23/2022 CHRISTOPHE COCHRAN
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 10/19/2021 RIDWAN HARDY
Address approval Cleared 1/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/13/2022 CARLOS AGUILERA
Sewer availability Cleared 1/13/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/24/2022 LUISANGEL VALENZUELA

Contact Information

Contractor Fast Track Builders; Lic. No.: 1075351-B 10028 SHOUP AVE      CHATSWORTH, CA 91311
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/10/2022 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 5/11/2022 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 5/13/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/21/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 6/21/2022 Approved CHRISTOPHE COCHRAN
Insulation 6/27/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/27/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 6/27/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/1/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 7/1/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/1/2022 Approved CHRISTOPHE COCHRAN
Insulation 7/1/2022 Approved CHRISTOPHE COCHRAN
Shower Pan 7/1/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 7/7/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/7/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 10/5/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 12/2/2022 Approved CHRISTOPHE COCHRAN
Final 12/2/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 12/2/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 12/2/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 12/2/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/2/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 12/8/2022 Approved CHRISTOPHE COCHRAN
Final 12/8/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 12/8/2022 Approved CHRISTOPHE COCHRAN
HVAC-Final 12/8/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 12/8/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 12/23/2022 Approved CHRISTOPHE COCHRAN
Final 12/23/2022 OK to Issue CofO CHRISTOPHE COCHRAN
HVAC-Final 12/23/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 12/23/2022 Approved CHRISTOPHE COCHRAN
Service/Power Release 12/23/2022 Approved CHRISTOPHE COCHRAN
Service/Power Release 1/9/2023 Approved CHRISTOPHE COCHRAN