5117 N STROHM AVE 91601
Certificate Information: 5117 N STROHM AVE 91601
- Application / Permit
- 21016-20000-36458
- Plan Check / Job No.
- B21VN13737
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE FRONT PORCH AREAS FOR DINING ROOM AND KITCHEN EXTENSION, AND CREATE A (N) ENTRANCE DOOR. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/26/2022
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/12/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/9/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/10/2021 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/28/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| Issued | 1/13/2022 | APPLICANT |
| Permit Finaled | 8/25/2022 | JOHN HAYES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Kyra Construction Inc; Lic. No.: 1057558-B | 15233 VENTURA BLVD #705 SHERMAN OAKS, CA 91403 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2022 | Approved | ARAM AVEDISIAN |
| Wood Frame | 2/16/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/20/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/20/2022 | Approved | ARAM AVEDISIAN |
| Wood Frame | 4/20/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 4/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/2/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/2/2022 | Approved | MICHEL ABAJAN |
| Insulation | 5/4/2022 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/9/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/7/2022 | Approved | CALEB MEISTER |
| Insulation | 6/13/2022 | Approved | MICHAEL SMITH |
| Drywall Nailing | 6/17/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 6/17/2022 | Approved | JOHN HAYES |
| Final | 8/25/2022 | Permit Finaled | JOHN HAYES |
| Green Building Final | 8/25/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 8/25/2022 | Approved | JOHN HAYES |