9908 N O'MELVENY AVE 91331
Certificate Information: 9908 N O'MELVENY AVE 91331
- Application / Permit
- 21016-20000-36348
- Plan Check / Job No.
- B21VN13698
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) REC. ROOM AND STORAGE INTO A ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | PINANK PATEL |
| Corrections Issued | 10/17/2021 | PINANK PATEL |
| Plan Check Approved | 11/1/2021 | PINANK PATEL |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| CofO in Progress | 6/15/2022 | MICHEL ABAJAN |
| Permit Finaled | 6/20/2022 | MICHAEL SMITH |
| CofO Issued | 6/20/2022 | MICHAEL SMITH |
| Permit Finaled | 6/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 10/20/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/25/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 1/25/2022 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/4/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/4/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/4/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 3/4/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/4/2022 | Approved | MICHEL ABAJAN |
| Insulation | 3/8/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/24/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/24/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/24/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| Final | 6/2/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/2/2022 | Approved | MICHEL ABAJAN |
| Final | 6/15/2022 | OK to Issue CofO | MICHEL ABAJAN |