5913 N CAHILL AVE 91356
Certificate Information: 5913 N CAHILL AVE 91356
- Application / Permit
- 21016-20000-36296
- Plan Check / Job No.
- B21VN13660
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL THE (E) SINGLE FAMILY DWELLING AND CONVERT THE (E) ATTACHED GARAGE INTO A (N) MASTER BEDROOM.
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2021 | COLIN LOREDO |
| Corrections Issued | 10/12/2021 | COLIN LOREDO |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| Plan Check Approved | 11/2/2021 | COLIN LOREDO |
| Issued | 11/9/2021 | APPLICANT |
| CofO in Progress | 2/10/2022 | SEAN HAUPT |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
| CofO Issued | 3/6/2022 | MICHAEL SMITH |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hold | Cleared | 10/18/2021 | JASON SHEETS |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/1/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 12/10/2021 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 12/10/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/14/2021 | Approved | SEAN HAUPT |
| HVAC-Rough | 12/14/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/20/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/20/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/20/2021 | Approved | SEAN HAUPT |
| Insulation | 1/10/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 1/13/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/13/2022 | Approved | SEAN HAUPT |
| Shower Pan | 1/13/2022 | Approved | SEAN HAUPT |
| Final | 1/31/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 1/31/2022 | Corrections Issued | JUSTIN HAWLEY |
| Final | 2/2/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 2/2/2022 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Final | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 2/8/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Final | 2/9/2022 | Approved | SEAN HAUPT |
| Final | 2/9/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 2/9/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 2/9/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 2/9/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 2/9/2022 | Approved | SEAN HAUPT |