6636 N GENTRY AVE 91606
Certificate Information: 6636 N GENTRY AVE 91606
- Application / Permit
- 21016-20000-36259
- Plan Check / Job No.
- B21VN13630
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING GARAGE CONVERSION TO ADU 20' X 18' (360 SQ. FT.) AND ADDITION OF 14'-2"X20'-2" (285 SQ.FT.) TOTAL FINISHED ADU 645 S.F. PER ORDINANCE.
- Permit Issued
- Issued on 6/27/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2021 | MICHAEL LOPEZ |
| Corrections Issued | 10/22/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/5/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/10/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/13/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 6/22/2022 | MICHAEL LOPEZ |
| Issued | 6/27/2022 | APPLICANT |
| CofO in Progress | 11/22/2022 | ARAM AVEDISIAN |
| CofO Issued | 3/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2021 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 11/19/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 12/21/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2022 | AMIR KASHFI |
| Construction within easement | Cleared | 3/13/2022 | RIDWAN HARDY |
Contact Information
| Architect | Lancy,, Lawrence M; Lic. No.: NA27720 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/6/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 7/14/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 7/29/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Conditional Approval | CALEB MEISTER |
| HVAC-Rough | 7/29/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 7/29/2022 | Approved | CALEB MEISTER |
| Deputy Wood Construction | 8/1/2022 | Conditional Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 8/3/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Rough | 8/3/2022 | Not Ready for Inspection | ALAN MORELOS |
| HVAC-Rough | 8/3/2022 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 8/3/2022 | Not Ready for Inspection | ALAN MORELOS |
| Shower Pan | 8/3/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/29/2022 | Approved Pending GreenApproval | JOHN HAYES |
| Green Building Rough | 8/29/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/29/2022 | Approved | JOHN HAYES |
| Insulation | 9/2/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 9/2/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/6/2022 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 9/9/2022 | Approved | CALEB MEISTER |
| Gas Test | 9/9/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/15/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 10/25/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/25/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/25/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/25/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | JOHN HAYES |
| BUILDING-Rough-Frame | 11/15/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/15/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/15/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/15/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Final | 11/22/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 11/22/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/22/2022 | Approved | ARAM AVEDISIAN |