9991-9993 N STANWIN AVE 91331

Certificate Information: 9991-9993 N STANWIN AVE 91331

Application / Permit
21016-20000-34332
Plan Check / Job No.
B21VN13525
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2021 APPLICANT
Assigned to Plan Check Engineer 10/15/2021 JEROME MAGAT PALMA
Corrections Issued 10/16/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 11/4/2021 JEROME MAGAT PALMA
Plan Check Approved 12/30/2021 JEROME MAGAT PALMA
Building Plans Picked Up 12/30/2021 APPLICANT
Issued 1/5/2022 APPLICANT
CofO in Progress 7/14/2023 MICHEL ABAJAN
Permit Finaled 7/18/2023 RONALD MYRICK
CofO Issued 7/18/2023 RONALD MYRICK
Permit Finaled 7/18/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/1/2021 AMIR KASHFI
Sewer availability Cleared 12/1/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 12/2/2021 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/19/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 1/24/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 1/24/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 2/11/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/11/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 3/11/2022 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 3/18/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 3/18/2022 Partial Approval MICHEL ABAJAN
Pre-Inspection 3/18/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 3/29/2022 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 3/29/2022 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 4/8/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 4/8/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/12/2022 Approved MICHEL ABAJAN
Green Building Rough 4/12/2022 Approved MICHEL ABAJAN
METHANE-Rough 4/12/2022 Approved MICHEL ABAJAN
Insulation 4/29/2022 Approved MICHEL ABAJAN
Drywall Nailing 5/20/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/15/2023 Approved MICHEL ABAJAN
Final 6/15/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 6/15/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 6/15/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/30/2023 Approved MICHEL ABAJAN
Final 6/30/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 6/30/2023 Approved MICHEL ABAJAN
PLUMBING-Final 6/30/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Approved MICHEL ABAJAN
Final 7/14/2023 OK to Issue CofO MICHEL ABAJAN