12007 W DEWEY ST 90066

Certificate Information: 12007 W DEWEY ST 90066

Application / Permit
21016-20000-32862
Plan Check / Job No.
B21VN13414
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL THROUGHOUT DWELLING. REMOVE AND REPLACE DOORS AND WINDOWS. REMOVE WALL AT KITCHEN. REMODEL KITCHEN AND TWO BATHROOMS.
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
Permit Finaled on 9/9/2022

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/12/2021 JEROME MAGAT PALMA
Corrections Issued 10/13/2021 JEROME MAGAT PALMA
Plan Check Approved 11/4/2021 JEROME MAGAT PALMA
Issued 11/4/2021 APPLICANT
Building Plans Picked Up 11/5/2021 APPLICANT
Permit Finaled 9/8/2022 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/4/2021 JEROME MAGAT PALMA

Contact Information

Contractor Cody Construction; Lic. No.: 635477-B 26210 FAIRSIDE RD      MALIBU, CA 90265
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/1/2022 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 3/10/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 3/10/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 3/10/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/10/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 3/31/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 3/31/2022 Approved JOHNNY MIRANDA
HVAC-Rough 3/31/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/31/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/31/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 4/8/2022 Approved JOHNNY MIRANDA
Green Building Rough 4/8/2022 Approved JOHNNY MIRANDA
Insulation 4/8/2022 Approved JOHNNY MIRANDA
Drywall Nailing 4/15/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/10/2022 Corrections Issued JOHNNY MIRANDA
Shower Pan 5/10/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/11/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 8/24/2022 Approved ANDREW NAVE
Final 8/24/2022 Not Ready for Inspection ANDREW NAVE
HVAC-Final 8/24/2022 Approved ANDREW NAVE
PLUMBING-Final 8/24/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 8/24/2022 Approved ANDREW NAVE
Final 9/8/2022 Permit Finaled JOHNNY MIRANDA
PLUMBING-Final 9/8/2022 Approved JOHNNY MIRANDA