5642-5644 N MAYNARD AVE 91367
Certificate Information: 5642-5644 N MAYNARD AVE 91367
- Application / Permit
- 21016-20000-32847
- Plan Check / Job No.
- B21VN13388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' X 20' ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 11/19/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2021 | JEFFREY TANGONAN |
| Corrections Issued | 10/5/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 10/21/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 11/5/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| Issued | 11/19/2021 | APPLICANT |
| CofO in Progress | 5/12/2022 | TROY SANDERS |
| CofO Issued | 6/8/2022 | JOHN JANSON |
| Permit Finaled | 6/8/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/3/2021 | Partial Approval | TROY SANDERS |
| Pre-Inspection | 12/3/2021 | Approved | TROY SANDERS |
| Deputy Other (see comments) | 12/27/2021 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 12/29/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 2/17/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | TROY SANDERS |
| Gas Test | 2/17/2022 | Approved | TROY SANDERS |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 2/17/2022 | Approved | TROY SANDERS |
| Insulation | 2/17/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 2/17/2022 | Approved | TROY SANDERS |
| Gas Test | 2/28/2022 | Approved | TROY SANDERS |
| Insulation | 2/28/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 3/4/2022 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 5/11/2022 | Approved | TROY SANDERS |
| Final | 5/11/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 5/11/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/11/2022 | Approved | TROY SANDERS |
| HVAC-Final | 5/11/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/11/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/11/2022 | Approved | TROY SANDERS |