5045 N DONNA AVE 91356

Certificate Information: 5045 N DONNA AVE 91356

Application / Permit
21016-20000-32658
Plan Check / Job No.
B21VN13326
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 8'-0" X 20'-0" TO RELOCATE AND ADD NEW KITCHEN/PANRY, ENCLOSE 4'-0" X 11'-9" FOR NEW FRONT ENTRY, CONVERT (E) 10'-0" X 30'-0" ATTACHED PATIO COVER TO (N) STUDY ROOM, CONVERT (E) BEDROOM/BATHROOM/CLOSET TO (N) KITCHEN/PANTRY/LAUNDRY ROOM, CONVERT (E) FAMILY ROOM/KITCHEN TO (N) BEDROOM, REMODEL (E) BATHROOMS, REMODEL THROUGHOUT (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/21/2021
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2021 APPLICANT
Assigned to Plan Check Engineer 10/1/2021 JENNIFER LEE
Corrections Issued 10/1/2021 JENNIFER LEE
Applicant returned to address corrections 10/26/2021 JENNIFER LEE
Applicant returned to address corrections 11/9/2021 JENNIFER LEE
Applicant returned to address corrections 11/29/2021 JENNIFER LEE
Applicant returned to address corrections 12/7/2021 JENNIFER LEE
Plan Check Approved 12/21/2021 JENNIFER LEE
Issued 12/21/2021 APPLICANT
Building Plans Picked Up 12/23/2021 APPLICANT
CofO in Progress 8/3/2022 DAVID SANDOVAL
Permit Finaled 9/10/2022 MICHAEL SMITH
CofO Issued 9/10/2022 MICHAEL SMITH
Permit Finaled 9/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 10/29/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 11/2/2021 ALEXANDER ANDREWS

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/11/2022 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 1/14/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 1/14/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 1/21/2022 Not Ready for Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 1/21/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 1/21/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 1/25/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 1/26/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 1/28/2022 Not Ready for Inspection PETER FOLLING
Excavation/Setback/Form/Re-Bar 1/28/2022 Partial Approval PETER FOLLING
PLUMBING-Rough 1/28/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 2/1/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 2/1/2022 No Access for Inspection DAVID SANDOVAL
PLUMBING-Rough 2/1/2022 Not Ready for Inspection DAVID SANDOVAL
Pre-Inspection 2/7/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 2/17/2022 Approved DAVID SANDOVAL
Underground Mechanical 2/17/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/22/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 2/22/2022 Not Ready for Inspection DAVID SANDOVAL
Wood Frame 2/22/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 3/10/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/10/2022 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 3/14/2022 Partial Inspection DAVID SANDOVAL
ELECTRICAL-Rough 3/14/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Inspection DAVID SANDOVAL
Green Building Rough 3/14/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/14/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 3/18/2022 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 3/18/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/18/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 3/25/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Approved DAVID SANDOVAL
Green Building Rough 3/25/2022 Approved DAVID SANDOVAL
HVAC-Rough 3/25/2022 Approved DAVID SANDOVAL
Insulation 3/30/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/30/2022 Not Ready for Inspection MORRIS JACKSON
Shower Pan 3/30/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/5/2022 Approved MORRIS JACKSON
Drywall Nailing 4/6/2022 Approved MORRIS JACKSON
Final 6/23/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 6/23/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 6/23/2022 Approved DAVID SANDOVAL
Final 6/28/2022 Partial Approval DAVID SANDOVAL
Final 8/2/2022 OK to Issue CofO DAVID SANDOVAL