9330 N WINNETKA AVE 91311

Certificate Information: 9330 N WINNETKA AVE 91311

Application / Permit
21016-20000-32634
Plan Check / Job No.
B21VN13319
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Wholesale Business
Work Description
*ePlan Check* Tenant improvement to (E) wholesales space. Work to include new sales floor fixtures and fixture reflow, demo of existing sales floor finishes,(ie: paint, carpet, graphics, etc.) fixture anchoring & seismic plans for fixtures Re-stripting parking lot and addition of a new ramp
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
Permit Finaled on 4/24/2023

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/12/2021 MONICA RAMIREZ
Corrections Issued 10/13/2021 MONICA RAMIREZ
Applicant returned to address corrections 12/9/2021 MONICA RAMIREZ
Applicant returned to address corrections 2/28/2022 MONICA RAMIREZ
Applicant returned to address corrections 3/9/2022 MONICA RAMIREZ
Plan Check Approved 4/11/2022 MONICA RAMIREZ
Issued 4/13/2022 APPLICANT
Permit Finaled 4/21/2023 DEANDRE HOFFMAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/10/2022 CARLOS AGUILERA
DAS Clearance Cleared 2/23/2022 MONICA RAMIREZ

Contact Information

Architect Blees,, Patrick G; Lic. No.: NA31531       ,
Contractor Rapid Fix Inc; Lic. No.: 780169-B       ,
Engineer Buchanan,, David Charles; Lic. No.: C67437 2509 IRVING AVE S      MINNEAPOLIS, MN 55405

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Final 5/6/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 5/6/2022 Approved JEFFREY FULTON
Final 8/31/2022 Corrections Issued JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Not Ready JEFFREY FULTON
Footing/Foundation/Slab 2/1/2023 Not Ready for Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 2/14/2023 Approved DEANDRE HOFFMAN
Footing/Foundation/Slab 2/14/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/15/2023 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 2/21/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/22/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/3/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Other (see comments) 3/24/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/24/2023 Conditional Approval DEANDRE HOFFMAN
Final 4/20/2023 No Access for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Not Ready DEANDRE HOFFMAN
Final 4/21/2023 Permit Finaled DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved DEANDRE HOFFMAN