441-443 E TERRILL AVE 90042

Certificate Information: 441-443 E TERRILL AVE 90042

Application / Permit
21016-20000-32214
Plan Check / Job No.
B21VN13188
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE (20' X 20', 400SF) TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) & 65852.22
Permit Issued
Issued on 1/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 NILOOFAR MEHRAIN
Corrections Issued 11/2/2021 NILOOFAR MEHRAIN
Quality Review Completed 11/9/2021 STEVEN KIM
Building Plans Picked Up 12/3/2021 APPLICANT
Applicant returned to address corrections 11/15/2022 NILOOFAR MEHRAIN
Plan Check Approved 1/13/2023 NILOOFAR MEHRAIN
Issued 1/18/2023 APPLICANT
CofO in Progress 9/6/2023 AMY COLIN
Permit Finaled 9/8/2023 RONALD MYRICK
Permit Finaled 9/8/2023 RONALD MYRICK
CofO Issued 9/8/2023 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/28/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 4/28/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 4/28/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 4/28/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 4/28/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 4/28/2022 AMAAN MALIK
Sewer availability Cleared 4/28/2022 AMAAN MALIK
Address approval Cleared 5/3/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/3/2022 AMAAN MALIK
"D" conditions Cleared 6/16/2022 DANIEL CORONADO
"Q" conditions Cleared 6/16/2022 DANIEL CORONADO
ZI Cleared 6/16/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 7/17/2022 RUEL COLE
Grading Pre-Inspection Cleared 7/26/2022 KIRK LINKLATER
GPI Written Notices Cleared 11/15/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/13/2023 Approved AMY COLIN
PLUMBING-Rough 3/13/2023 Partial Approval AMY COLIN
ELECTRICAL-Rough 3/22/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 3/28/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/4/2023 Approved AMY COLIN
Green Building Rough 4/4/2023 Approved AMY COLIN
Interior/Exterior Lathing 4/4/2023 Partial Approval AMY COLIN
PLUMBING-Rough 4/4/2023 Approved AMY COLIN
Insulation 4/6/2023 Corrections Issued AMY COLIN
Insulation 4/10/2023 Approved AMY COLIN
Interior/Exterior Lathing 4/14/2023 Approved AMY COLIN
Drywall Nailing 4/18/2023 Approved AMY COLIN
Shower Pan 4/18/2023 Approved AMY COLIN
Interior/Exterior Lathing 4/24/2023 Approved AMY COLIN
ELECTRICAL-Final 6/1/2023 Corrections Issued AMY COLIN
Final 6/1/2023 Corrections Issued AMY COLIN
Green Building Final 6/1/2023 Not Ready for Inspection AMY COLIN
HVAC-Final 6/1/2023 Approved AMY COLIN
PLUMBING-Final 6/1/2023 Corrections Issued AMY COLIN
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 6/1/2023 Approved AMY COLIN
ELECTRICAL-Final 6/7/2023 Corrections Issued AMY COLIN
Final 6/7/2023 Not Ready for Inspection AMY COLIN
Green Building Final 6/7/2023 Approved AMY COLIN
HVAC-Final 6/7/2023 Approved AMY COLIN
PLUMBING-Final 6/7/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved AMY COLIN
Final 6/21/2023 Partial Approval AMY COLIN
Final 9/6/2023 OK to Issue CofO AMY COLIN