4426 N BEN AVE 91607
Certificate Information: 4426 N BEN AVE 91607
- Application / Permit
- 21016-20000-31044
- Plan Check / Job No.
- B21VN13000
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19' 2" X 18' 3" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | JESSE ARELLANO |
| Corrections Issued | 9/25/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| Issued | 2/6/2023 | APPLICANT |
| CofO in Progress | 2/3/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| CofO Issued | 3/6/2025 | RUBEN SALAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2023 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 1/26/2023 | JESSE ARELLANO |
Contact Information
| Contractor | Fleet Construction; Lic. No.: 868527-B | 4424 BEN AVENUE STUDIO CITY, CA 91607 |
| Engineer | Rodgers,, Rob J; Lic. No.: S4339 | 4539 BECK AVE STUDIO CITY, CA 91602 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/11/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 3/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 3/22/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 3/22/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 3/22/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/8/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/8/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 4/8/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/8/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 4/19/2024 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 4/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/7/2024 | Approved | SALVADOR MARTINEZ |
| Final | 10/16/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 10/16/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/16/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 11/18/2024 | Conditional Approval | DAVID MATSON |
| Green Building Final | 11/18/2024 | Approved | DAVID MATSON |
| Smoke Detectors | 11/18/2024 | Approved | DAVID MATSON |
| Final | 1/31/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |