12128 W OXNARD ST 91606
Certificate Information: 12128 W OXNARD ST 91606
- Application / Permit
- 21016-20000-31039
- Plan Check / Job No.
- B21VN12992
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING EXISTING DETACHED GARAGE TO ADU + 2-STORY ADDITION
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | JOE VO |
| Corrections Issued | 11/7/2021 | JOE VO |
| Quality Review Completed | 11/16/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/6/2021 | JOE VO |
| Plan Check Approved | 2/16/2022 | JOE VO |
| Issued | 3/25/2022 | APPLICANT |
| CofO in Progress | 6/5/2024 | JOSE AVILA |
| CofO Issued | 7/22/2024 | RUBEN SALAS |
| Permit Finaled | 7/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Highway dedication | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 2/8/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/8/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2022 | Approved | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/17/2022 | Corrections Issued | RAFAEL CORTES |
| PLUMBING-Rough | 8/17/2022 | Corrections Issued | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/23/2022 | Corrections Issued | RAFAEL CORTES |
| PLUMBING-Rough | 8/23/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 8/29/2022 | Partial Approval | RAFAEL CORTES |
| Sewer | 9/1/2022 | Approved | RAFAEL CORTES |
| Footing/Foundation/Slab | 11/14/2022 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 11/29/2022 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/22/2022 | Approved | WILLIAM WREN |
| Wood Frame | 4/18/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| Grounding or Bonding | 8/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 8/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 8/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 8/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/28/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 8/28/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 8/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 8/28/2023 | Corrections Issued | KIRK SANDERS |
| MERV13>=Rough | 8/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 8/28/2023 | Approved | KIRK SANDERS |
| Wood Frame | 8/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 10/25/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 10/27/2023 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/21/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/22/2024 | Partial Approval | JOSE AVILA |
| Green Building Final | 1/22/2024 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 1/22/2024 | Approved | JOSE AVILA |
| MERV13>=Final | 1/22/2024 | Approved | JOSE AVILA |
| MERV13>=Rough | 1/22/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 1/22/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 1/22/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 1/29/2024 | Corrections Issued | JOSE AVILA |
| Gas Test | 1/29/2024 | Approved | JOSE AVILA |
| HVAC-Final | 1/29/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 1/29/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 2/12/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 2/12/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV Not Ready | CRAIG DAVIS |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 3/4/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | JOSE AVILA |
| Final | 6/4/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 6/14/2024 | Approved | JOSE AVILA |