11162 N TAMARACK AVE 91331
Certificate Information: 11162 N TAMARACK AVE 91331
- Application / Permit
- 21016-20000-30939
- Plan Check / Job No.
- B21VN12911
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVESION OF GARAGE TO ADU PER ORDINANCE The LID clearance has been deferred. Approval for LID requirements shall be obtined from LASAN prior to the finaling of the permit
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 9/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2021 | HERNAN ARREOLA |
| Corrections Issued | 10/9/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/25/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/9/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/17/2021 | HERNAN ARREOLA |
| Issued | 12/30/2021 | APPLICANT |
| CofO in Progress | 7/26/2023 | MICHEL ABAJAN |
| CofO Issued | 9/11/2023 | RUBEN SALAS |
| Permit Finaled | 9/11/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/18/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/11/2022 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 3/31/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 3/31/2022 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/18/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 4/18/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 4/18/2022 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 5/6/2022 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 5/6/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/9/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/9/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 6/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/23/2022 | Conditional Approval | MICHEL ABAJAN |
| Green Building Rough | 6/23/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/23/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/23/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/1/2022 | Not Ready for Inspection | ROBERT GOLD |
| Drywall Nailing | 7/11/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Insulation | 7/11/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/22/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/6/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/6/2023 | Approved | MICHEL ABAJAN |
| Final | 1/6/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/6/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 1/6/2023 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/6/2023 | Approved | MICHEL ABAJAN |
| Final | 4/21/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/21/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/21/2023 | Approved | MICHEL ABAJAN |
| Final | 6/2/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/10/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 7/26/2023 | OK to Issue CofO | MICHEL ABAJAN |