12427 W EVERGLADE ST 90066
Certificate Information: 12427 W EVERGLADE ST 90066
- Application / Permit
- 21016-20000-30873
- Plan Check / Job No.
- B21VN12885
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-1" X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A)). ALL WORK PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/24/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/20/2022 | AUNG SOE |
| Plan Check Approved | 1/24/2022 | AUNG SOE |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| Issued | 2/14/2022 | APPLICANT |
| CofO in Progress | 9/11/2024 | JESUS PINEDA |
| Permit Finaled | 9/17/2024 | RICHARD STEINBACH |
| CofO Issued | 9/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/6/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 12/13/2021 | ALEXANDER ANDREWS |
| Construction near power lines | Cleared | 1/7/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/31/2022 | No Access for Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/7/2022 | Corrections Issued | PATRICK QUALEY |
| Deputy Drilled-In Anchors | 4/8/2022 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 4/29/2022 | Corrections Issued | PATRICK QUALEY |
| Sewer | 4/29/2022 | Corrections Issued | PATRICK QUALEY |
| Underground Mechanical | 4/29/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Approval | PATRICK QUALEY |
| PLUMBING-Rough | 5/23/2022 | Conditional Approval | PATRICK QUALEY |
| Shower Pan | 5/23/2022 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 6/3/2022 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/3/2022 | Approved | STEPHANIE SWANSON |
| Shower Pan | 6/3/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/7/2022 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 6/7/2022 | Conditional Approval | RICHARD STEINBACH |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | RICHARD STEINBACH |
| Insulation | 6/21/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Approved | PATRICK QUALEY |
| Drywall Nailing | 7/7/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/7/2022 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/8/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 8/30/2024 | Approved | JESUS PINEDA |
| Final | 8/30/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/30/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 8/30/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 8/30/2024 | Approved | JESUS PINEDA |
| Final | 9/10/2024 | OK to Issue CofO | JESUS PINEDA |