10692 N KEWEN AVE 91331
Certificate Information: 10692 N KEWEN AVE 91331
- Application / Permit
- 21016-20000-30807
- Plan Check / Job No.
- B21VN12853
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-6" X 26'-3" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/15/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/24/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/20/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/8/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 5/2/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Issued | 8/15/2022 | APPLICANT |
| CofO in Progress | 4/7/2023 | MICHEL ABAJAN |
| CofO Issued | 4/14/2023 | RONALD MYRICK |
| Permit Finaled | 4/14/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 1/28/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Krasuski,, Leszek; Lic. No.: C71358 | 18403 COLLINS ST D TARZANA, CA 91356 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/27/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/27/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/27/2022 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 10/27/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 10/27/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 10/27/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 11/7/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/15/2022 | Approved | MICHEL ABAJAN |
| Gas Test | 11/15/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/15/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 11/15/2022 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 11/15/2022 | Approved | MICHEL ABAJAN |
| Insulation | 11/21/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/21/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/1/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/8/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 1/26/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/17/2023 | Approved | MICHEL ABAJAN |
| Final | 2/17/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 2/17/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 2/17/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/17/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | MICHEL ABAJAN |
| Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/7/2023 | OK to Issue CofO | MICHEL ABAJAN |