8501 W HEDGES PL 90069
Certificate Information: 8501 W HEDGES PL 90069
- Application / Permit
- 21016-20000-30578
- Plan Check / Job No.
- B21VN12766
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX IRR 19'6"X11'9" BEDRM AT 1ST FLR INTO STORAGE ROOM W/ EXTERIOR GARAGE DOOR PER ENGR DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 09/16/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE." SEE COMMENTS.
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- CofO Issued on 3/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 9/26/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/10/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/26/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| Issued | 1/14/2022 | APPLICANT |
| CofO in Progress | 8/31/2022 | RAUL BARAJAS |
| Permit Finaled | 3/25/2023 | DANIEL ORRANTE |
| CofO Issued | 3/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/18/2021 | VASIL MIHALEV |
Contact Information
| Contractor | Wood Ryan Patrick; Lic. No.: 840125-B | 2000 EXECUTIVE DR PALM SPRINGS, CA 92262 |
| Engineer | Haddad,, Alexander H; Lic. No.: C76351 | 3528 DUNE LN LA VERNE, CA 91750 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 2/2/2022 | Corrections Issued | GORDON ZUBER |
| BUILDING-Rough-Frame | 3/16/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 3/30/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/12/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/12/2022 | Approved | RAUL BARAJAS |
| Final | 5/12/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 5/12/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 8/31/2022 | OK to Issue CofO | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 8/31/2022 | Approved | RAUL BARAJAS |