8213 N WYNNE AVE 91335
Certificate Information: 8213 N WYNNE AVE 91335
- Application / Permit
- 21016-20000-30172
- Plan Check / Job No.
- B21VN12554
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 20'x20' Detached Car Garage to A.D.U PER STATE LAW
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- Current Status
- CofO Issued on 6/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2021 | CARLOS MONTES |
| Corrections Issued | 11/4/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 2/24/2023 | DANIEL YIP |
| Plan Check Approved | 6/23/2023 | DANIEL YIP |
| Issued | 5/6/2025 | APPLICANT |
| CofO in Progress | 6/12/2026 | JUAN ALVARADO |
| Permit Finaled | 6/18/2026 | JOHN JANSON |
| CofO Issued | 6/18/2026 | JOHN JANSON |
| Permit Finaled | 6/18/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2023 | RYAN KIM |
| Sewer availability | Cleared | 3/2/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2023 | RYAN KIM |
| Construction near power lines | Cleared | 6/6/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/20/2025 | Conditional Approval | ROBERT GOLD |
| Deputy Reinf. Concrete | 5/20/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/20/2025 | Corrections Issued | JUAN ALVARADO |
| Sewer | 5/20/2025 | Approved | JUAN ALVARADO |
| Footing/Foundation/Slab | 5/29/2025 | Conditional Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/6/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 6/6/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 6/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 6/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 6/6/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/1/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/1/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 7/1/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 7/1/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/16/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 7/16/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 7/16/2025 | Approved | JUAN ALVARADO |
| Insulation | 7/16/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 7/22/2025 | Conditional Approval | JUAN ALVARADO |
| Shower Pan | 7/22/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 7/25/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/25/2025 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 5/26/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 5/26/2026 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 5/26/2026 | Approved | JUAN ALVARADO |
| HVAC-Final | 5/26/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 5/26/2026 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 5/26/2026 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 6/11/2026 | Approved | JUAN ALVARADO |
| Final | 6/11/2026 | OK to Issue CofO | JUAN ALVARADO |
| Service/Power Release | 6/11/2026 | Approved | JUAN ALVARADO |