10722 N NASSAU AVE 91040

Certificate Information: 10722 N NASSAU AVE 91040

Application / Permit
21016-20000-30167
Plan Check / Job No.
B21VN12550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO A DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/20/2021 CARLOS MONTES
Corrections Issued 9/20/2021 CARLOS MONTES
Applicant returned to address corrections 1/4/2022 CARLOS MONTES
Applicant returned to address corrections 1/5/2022 CARLOS MONTES
Plan Check Approved 1/13/2022 CARLOS MONTES
Issued 1/20/2022 APPLICANT
CofO in Progress 10/26/2022 MATTHEW NELSON
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/22/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/22/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/22/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/22/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 12/30/2021 RIDWAN HARDY
ZI Cleared 1/7/2022 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 3/22/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 4/6/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/18/2022 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 4/18/2022 Corrections Issued MATTHEW NELSON
Green Building Rough 4/18/2022 Corrections Issued MATTHEW NELSON
Interior/Exterior Lathing 4/18/2022 Not Ready for Inspection MATTHEW NELSON
Shower Pan 4/18/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/21/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/21/2022 Approved MATTHEW NELSON
Green Building Rough 4/21/2022 Approved MATTHEW NELSON
Insulation 4/26/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/26/2022 Approved MATTHEW NELSON
Drywall Nailing 4/28/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 5/23/2022 Corrections Issued MATTHEW NELSON
Final 10/13/2022 Corrections Issued MATTHEW NELSON
Green Building Final 10/13/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 10/13/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 10/26/2022 Approved MATTHEW NELSON
Final 10/26/2022 OK to Issue CofO MATTHEW NELSON
HVAC-Final 10/26/2022 Approved MATTHEW NELSON
PLUMBING-Final 10/26/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved MATTHEW NELSON