10722 N NASSAU AVE 91040
Certificate Information: 10722 N NASSAU AVE 91040
- Application / Permit
- 21016-20000-30167
- Plan Check / Job No.
- B21VN12550
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO A DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2021 | CARLOS MONTES |
| Corrections Issued | 9/20/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 1/4/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 1/5/2022 | CARLOS MONTES |
| Plan Check Approved | 1/13/2022 | CARLOS MONTES |
| Issued | 1/20/2022 | APPLICANT |
| CofO in Progress | 10/26/2022 | MATTHEW NELSON |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/22/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 12/30/2021 | RIDWAN HARDY |
| ZI | Cleared | 1/7/2022 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/18/2022 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 3/22/2022 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 4/6/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/18/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/18/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 4/18/2022 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/18/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Shower Pan | 4/18/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/21/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/21/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/21/2022 | Approved | MATTHEW NELSON |
| Insulation | 4/26/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/26/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/28/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/23/2022 | Corrections Issued | MATTHEW NELSON |
| Final | 10/13/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/13/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 10/13/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 10/26/2022 | Approved | MATTHEW NELSON |
| Final | 10/26/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 10/26/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 10/26/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | MATTHEW NELSON |