13860-13862 W WEIDNER ST 91331

Certificate Information: 13860-13862 W WEIDNER ST 91331

Application / Permit
21016-20000-30158
Plan Check / Job No.
B21VN12548
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
CofO Issued on 9/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Corrections Issued 9/17/2021 CARLOS MONTES
Assigned to Plan Check Engineer 9/20/2021 CARLOS MONTES
Corrections Issued 10/19/2021 CARLOS MONTES
Plan Check Approved 11/5/2021 CARLOS MONTES
Issued 11/18/2021 APPLICANT
CofO in Progress 9/13/2022 MICHEL ABAJAN
Permit Finaled 9/15/2022 DANIEL ORRANTE
CofO Issued 9/15/2022 DANIEL ORRANTE
Permit Finaled 9/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/23/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/23/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/28/2021 DAGOVERTO GUERRERO
Clean Up Green Up Cleared 10/25/2021 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2021 Partial Approval MICHEL ABAJAN
Gas Test 1/6/2022 Approved MICHEL ABAJAN
Pre-Inspection 1/6/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/11/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 1/14/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/27/2022 Not Ready for Inspection MICHEL ABAJAN
Wood Frame 2/22/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 3/21/2022 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/21/2022 No Access for Inspection MICHEL ABAJAN
Green Building Rough 3/21/2022 No Access for Inspection MICHEL ABAJAN
METHANE-Rough 3/21/2022 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 3/21/2022 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/23/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 3/23/2022 Approved MICHEL ABAJAN
Wood Frame 3/29/2022 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 4/8/2022 Approved MICHEL ABAJAN
Green Building Rough 4/8/2022 Approved MICHEL ABAJAN
HVAC-Rough 4/8/2022 Approved MICHEL ABAJAN
METHANE-Rough 4/8/2022 Approved MICHEL ABAJAN
Insulation 4/12/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/12/2022 Approved MICHEL ABAJAN
Drywall Nailing 4/15/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/18/2022 Approved MICHEL ABAJAN
Service/Power Release 6/15/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 8/18/2022 Not Ready for Inspection MICHEL ABAJAN
Final 8/18/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 8/18/2022 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 8/18/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 8/18/2022 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 8/18/2022 Not Ready for Inspection MICHEL ABAJAN
Final 9/6/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 9/6/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/6/2022 Approved MICHEL ABAJAN
Final 9/12/2022 OK to Issue CofO MICHEL ABAJAN