2015-2015 1/2 S RAYMOND AVE 90007
Certificate Information: 2015-2015 1/2 S RAYMOND AVE 90007
- Application / Permit
- 21016-20000-30148
- Plan Check / Job No.
- B21VN12532
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) ATT. TW0-CAR GARAGE AND PORTION OF LAUNDRY ROOM, STORAGE AND ENTERY AREA OF (E) UNITS AT 1ST FLOOR TO NEW ACCESSORY DWELLING UNIT [720.68 SF] PER CA Govt. Code 65852.2(e)(1)(C); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | SEAN SHAHMIRI |
| Corrections Issued | 10/18/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 10/26/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/29/2021 | APPLICANT |
| Applicant returned to address corrections | 12/15/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 12/20/2021 | SEAN SHAHMIRI |
| Issued | 1/26/2022 | APPLICANT |
| CofO in Progress | 1/16/2024 | KATHRYN BUTTERWORTH |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/14/2021 | ABEL CASILLAS |
Contact Information
| Contractor | Franz W R; Lic. No.: 911706-B | 26407 BOUQUET CANYON #25 SANTA CLARITA, CA 91350 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/25/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/7/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/7/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/14/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/19/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Gas Test | 7/19/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/19/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Shower Pan | 7/19/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/24/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/24/2023 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 7/24/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/24/2023 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 7/24/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/24/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 7/26/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 7/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/27/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 7/31/2023 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 7/31/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/4/2023 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 8/4/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 8/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | BRENDAN MORELLI |
| Final | 9/26/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 9/26/2023 | Approved | BRENDAN MORELLI |
| MERV13>=Final | 9/26/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 9/26/2023 | Approved | BRENDAN MORELLI |
| Final | 1/11/2024 | OK to Issue CofO | KATHRYN BUTTERWORTH |