9625 W CRESTA DR 90035
Certificate Information: 9625 W CRESTA DR 90035
- Application / Permit
- 21016-20000-30131
- Plan Check / Job No.
- B21VN12519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHEDF GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 1/31/2022
- Issuing Office
- Current Status
- CofO Issued on 8/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | SERGIO MUNIZ |
| Corrections Issued | 9/18/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 1/11/2022 | SERGIO MUNIZ |
| Plan Check Approved | 1/31/2022 | SERGIO MUNIZ |
| Issued | 1/31/2022 | APPLICANT |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| CofO in Progress | 8/26/2022 | OGANES TARAKHCHYAN |
| CofO Issued | 8/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 9/24/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 9/28/2021 | TIMOTHY POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | NIKTA MOUSAVI |
| Construction near power lines | Cleared | 1/30/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/7/2022 | No Result Entered | RONALD WEBER |
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 3/8/2022 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/11/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/11/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/11/2022 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/28/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/28/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 4/28/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/28/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/10/2022 | No Result Entered | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 5/10/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/13/2022 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/19/2022 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | KENNETH NAGLE |
| Green Building Rough | 5/24/2022 | Approved | KENNETH NAGLE |
| Insulation | 5/26/2022 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 5/27/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 6/2/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/7/2022 | Approved | EVAN COOPER |
| Shower Pan | 6/7/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 8/19/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Final | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/19/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 8/25/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |
| HVAC-Final | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/25/2022 | Approved | OGANES TARAKHCHYAN |