9625 W CRESTA DR 90035

Certificate Information: 9625 W CRESTA DR 90035

Application / Permit
21016-20000-30131
Plan Check / Job No.
B21VN12519
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHEDF GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 1/31/2022
Issuing Office
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 SERGIO MUNIZ
Corrections Issued 9/18/2021 SERGIO MUNIZ
Applicant returned to address corrections 1/11/2022 SERGIO MUNIZ
Plan Check Approved 1/31/2022 SERGIO MUNIZ
Issued 1/31/2022 APPLICANT
Building Plans Picked Up 2/2/2022 APPLICANT
CofO in Progress 8/26/2022 OGANES TARAKHCHYAN
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/24/2021 NIKTA MOUSAVI
Sewer availability Cleared 9/24/2021 NIKTA MOUSAVI
Grading Pre-Inspection Cleared 9/28/2021 TIMOTHY POWELL
Eng Process Fee Ord 176,300 Cleared 10/1/2021 NIKTA MOUSAVI
Construction near power lines Cleared 1/30/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 7919 SAUSALITO AVE      WEST HILLS, CA 91304

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/7/2022 No Result Entered RONALD WEBER
Excavation/Setback/Form/Re-Bar 3/8/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 3/8/2022 Corrections Issued KEVIN SARGSYAN
Sewer 3/8/2022 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/11/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 3/11/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 3/11/2022 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 4/15/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/15/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 4/28/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 4/28/2022 Approved KEVIN SARGSYAN
Green Building Rough 4/28/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/28/2022 Approved KEVIN SARGSYAN
Deputy Wood Construction 5/10/2022 No Result Entered RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 5/10/2022 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 5/10/2022 Approved KEVIN SARGSYAN
Deputy Wood Construction 5/13/2022 Conditional Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 5/16/2022 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Approved KEVIN SARGSYAN
Green Building Rough 5/16/2022 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 5/19/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 5/24/2022 Approved KENNETH NAGLE
Green Building Rough 5/24/2022 Approved KENNETH NAGLE
Insulation 5/26/2022 Corrections Issued KEVIN SARGSYAN
Insulation 5/27/2022 Approved KEVIN SARGSYAN
Drywall Nailing 6/2/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/7/2022 Approved EVAN COOPER
Shower Pan 6/7/2022 Approved EVAN COOPER
ELECTRICAL-Final 8/19/2022 Approved OGANES TARAKHCHYAN
Final 8/19/2022 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 8/19/2022 Approved OGANES TARAKHCHYAN
METHANE-Final 8/19/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 8/19/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 8/19/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Final 8/25/2022 OK to Issue CofO OGANES TARAKHCHYAN
HVAC-Final 8/25/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 8/25/2022 Approved OGANES TARAKHCHYAN