1719 S KELTON AVE 90024
Certificate Information: 1719 S KELTON AVE 90024
- Application / Permit
- 21016-20000-30038
- Plan Check / Job No.
- B21VN12476
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR/EXTERIOR REMODEL TO THE (E)2-STORY DUPLEX. ENCLOSE (E)CLOSET AT UNIT# 1721 TO BECOME PART OF THE BATHROOM AT UNIT# 1719 AT FIRST FLOOR. REMODEL KITCHEN, BEDROOMS AND BATHROOMS AT UNIT# 1719. CHANGE OUT WINDOWS & DOORS AT UNIT# 1719.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/18/2022
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 9/29/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 9/30/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/24/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 2/15/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Plan Check Approved | 3/17/2022 | SARKIS HARABEDIAN |
| Issued | 3/17/2022 | APPLICANT |
| Permit Finaled | 11/17/2022 | ASHLEY THOMPSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/27/2021 | SARKIS HARABEDIAN |
| "Q" conditions | Cleared | 2/7/2022 | KEVIN FULTON |
| Specific Plan | Cleared | 2/7/2022 | KEVIN FULTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/23/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/23/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/23/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/25/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/31/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/11/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/11/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/11/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/11/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/11/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/19/2022 | Approved | RICHARD STEINBACH |
| Pre-Inspection | 5/5/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/16/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/19/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 9/19/2022 | Approved | JOHN KIDWELL |
| Final | 11/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Ready | ASHLEY THOMPSON |
| Special/Order Compliance | 11/14/2022 | Corrections Issued | MICHAEL PELHAM |
| Final | 11/17/2022 | Permit Finaled | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | ASHLEY THOMPSON |