2310 1/8 E 3RD ST 90033
Certificate Information: 2310 1/8 E 3RD ST 90033
- Application / Permit
- 21016-20000-30036
- Plan Check / Job No.
- B21VN12475
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)and (e) IN (E) 3-UNIT APARTMENT.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | SERGIO MUNIZ |
| Corrections Issued | 9/18/2021 | SERGIO MUNIZ |
| Plan Check Approved | 1/26/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 4/22/2025 | RONALD JIMENEZ |
| CofO Issued | 4/23/2025 | ERNESTO CORRAL |
| Permit Finaled | 4/23/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 9/24/2021 | MICAELA TORRES-GIL |
| Grading Pre-Inspection | Cleared | 10/8/2021 | PATRICK MISCHLICH |
| Sewer availability | Cleared | 10/14/2021 | CECILIO NAVARRO |
| Redevelopment Project Area | Cleared | 11/18/2021 | GRACIELA ACOSTA |
| Address approval | Cleared | 1/12/2022 | THAN WIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | THAN WIN |
Contact Information
| Contractor | D L T Construction; Lic. No.: 890424-B | 6000 S AVALON BLVD LOS ANGELES, CA 90003 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 4/8/2022 | Not Ready for Inspection | MARK FERRARI |
| METHANE-Rough | 4/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 4/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Final | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Green Building Final | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Green Building Rough | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| METHANE-Final | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| METHANE-Rough | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Not Ready | JULIAN CAPUCETTI |
| Smoke Detectors | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Wood Frame | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Green Building Rough | 12/8/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 12/8/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 12/8/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 1/12/2024 | Partial Approval | RICARDO ROBLES |
| METHANE-Rough | 1/12/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Wood Frame | 1/12/2024 | Partial Approval | RICARDO ROBLES |
| Final | 8/22/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 8/22/2024 | Approved | RONALD JIMENEZ |
| Green Building Rough | 8/22/2024 | Approved | RONALD JIMENEZ |
| METHANE-Final | 8/22/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| METHANE-Rough | 8/22/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 8/22/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 8/22/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 10/3/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| METHANE-Final | 10/3/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| METHANE-Rough | 10/3/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 10/3/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 11/22/2024 | Conditional Approval | RONALD JIMENEZ |
| METHANE-Final | 11/22/2024 | Approved | RONALD JIMENEZ |
| METHANE-Rough | 11/22/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 11/22/2024 | Approved | RONALD JIMENEZ |
| Final | 2/10/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 2/14/2025 | OK to Issue CofO | RONALD JIMENEZ |