7609 W BEVERLY BLVD 90036
Certificate Information: 7609 W BEVERLY BLVD 90036
- Application / Permit
- 21016-20000-29685
- Plan Check / Job No.
- B21VN12443
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Pet Store
- Work Description
- CHANGE OF USE FROM RETAIL TO PET GROOMING STORE WITH NEW NON-LOAD BEARING INTERIOR PARTITIONS AND FINISHES. EXISTING TYPE III-A, 1-STORY BUILDING.
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 9/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | COLIN LOREDO |
| Corrections Issued | 10/21/2021 | COLIN LOREDO |
| Quality Review Completed | 10/27/2021 | OMID HEDAYAT |
| Plan Check Approved | 1/11/2022 | COLIN LOREDO |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 7/29/2022 | KATY RAMIREZ |
| CofO Issued | 8/1/2022 | ERNESTO CORRAL |
| Permit Finaled | 8/1/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 10/21/2021 | COLIN LOREDO |
| ZA Case | Cleared | 10/25/2021 | KENTON TRINH |
| ZA Case | Cleared | 10/25/2021 | KENTON TRINH |
| Comm Cor/Mini-Mall | Cleared | 10/28/2021 | KENTON TRINH |
| ZI | Cleared | 11/5/2021 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/16/2021 | CHRISTOPHER ROCHA |
| DAS Clearance | Cleared | 1/6/2022 | OLLIE CARTER |
Contact Information
| Architect | Jacobs,, Michael Christopher; Lic. No.: C29962 | 25 HOPKE AVENUE HASTINGS ON HUDSON, NY 10706 |
| Contractor | Soria Crescencio; Lic. No.: 1045541-B | 13042 TERRABELLA ST PACOIMA, CA 91331 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 2/1/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 2/7/2022 | Approved | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 2/8/2022 | Conditional Approval | KATY RAMIREZ |
| Wood Frame | 3/17/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 3/21/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 3/23/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 5/3/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 5/12/2022 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 5/12/2022 | Approved | KATY RAMIREZ |
| Final | 5/18/2022 | Partial Inspection | KATY RAMIREZ |
| Final | 7/29/2022 | OK to Issue CofO | KATY RAMIREZ |