2750 1/2 S CLYDE AVE 90016
Certificate Information: 2750 1/2 S CLYDE AVE 90016
- Application / Permit
- 21016-20000-29018
- Plan Check / Job No.
- B21VN12374
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 18' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | JENNIFER LEE |
| Corrections Issued | 9/14/2021 | JENNIFER LEE |
| Plan Check Approved | 10/14/2021 | JENNIFER LEE |
| Issued | 10/15/2021 | APPLICANT |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| CofO in Progress | 3/3/2023 | JOSE AVILA |
| Permit Finaled | 3/6/2023 | DEROLD HAUFF |
| CofO Issued | 3/6/2023 | DEROLD HAUFF |
| Permit Finaled | 3/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/22/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/14/2022 | Not Ready for Inspection | JOSE AVILA |
| Underground Mechanical | 1/14/2022 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 2/28/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Approved | JOSE AVILA |
| Green Building Rough | 2/28/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 2/28/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 2/28/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/28/2022 | Corrections Issued | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 2/28/2022 | Partial Inspection | JOSE AVILA |
| PLUMBING-Rough | 4/1/2022 | Approved | JOSE AVILA |
| Insulation | 4/26/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/11/2022 | Approved | JOSE AVILA |
| Insulation | 5/13/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 5/27/2022 | Approved | JOSE AVILA |
| Green Building Rough | 5/27/2022 | Approved | JOSE AVILA |
| Final | 7/11/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 7/11/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 7/11/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 7/22/2022 | Approved | JOSE AVILA |
| Final | 7/22/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 7/22/2022 | Approved | JOSE AVILA |
| HVAC-Final | 7/22/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 7/22/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 7/22/2022 | Approved | JOSE AVILA |
| Final | 10/17/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 10/17/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 10/17/2022 | Approved | JOSE AVILA |
| Final | 3/3/2023 | OK to Issue CofO | JOSE AVILA |