17300-17302 W TUBA ST 91325

Certificate Information: 17300-17302 W TUBA ST 91325

Application / Permit
21016-20000-27803
Plan Check / Job No.
B21VN12364
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADU conversion. Convert (e) family room (473 SF) into a JrADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 11/2/2021
Issuing Office
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 MICHAEL LOPEZ
Corrections Issued 9/14/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 9/29/2021 MICHAEL LOPEZ
Plan Check Approved 10/26/2021 MICHAEL LOPEZ
Issued 11/2/2021 APPLICANT
CofO in Progress 3/19/2022 MICHAEL TEMPLE
CofO Issued 6/20/2022 MICHAEL SMITH
Permit Finaled 6/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/14/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/14/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/15/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/8/2021 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 11/8/2021 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 12/2/2021 Approved MARK JOHNSON
Underground Mechanical 12/2/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 12/21/2021 Approved MATTHEW NELSON
Green Building Rough 12/21/2021 Approved MATTHEW NELSON
Rough-Elec/Plmb/HVAC 12/21/2021 Approved MATTHEW NELSON
Insulation 12/27/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/27/2021 Partial Approval KRISTEN CAUSEY
PLUMBING-Rough 12/27/2021 Partial Inspection KRISTEN CAUSEY
Shower Pan 12/27/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/3/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 1/10/2022 Approved MARK JOHNSON
Final 3/4/2022 Corrections Issued RAUL OLAGI
Green Building Final 3/4/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved RAUL OLAGI
Final 3/14/2022 OK to Issue CofO MICHAEL TEMPLE
Green Building Final 3/14/2022 Approved MICHAEL TEMPLE
Smoke Detectors 3/14/2022 Approved MICHAEL TEMPLE