1843 1/2 W 71ST ST 90047
Certificate Information: 1843 1/2 W 71ST ST 90047
- Application / Permit
- 21016-20000-27724
- Plan Check / Job No.
- B21VN12345
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 19' X 24'-6" (468 SQ. FT.) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 5/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/13/2021 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 9/20/2021 | APPLICANT |
| Plan Check Approved | 3/9/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 5/24/2023 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/28/2023 | DEROLD HAUFF |
| CofO Issued | 5/28/2023 | DEROLD HAUFF |
| Permit Finaled | 5/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2021 | WALLIE JONG |
| Sewer availability | Cleared | 11/2/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | WALLIE JONG |
| Construction near power lines | Cleared | 2/26/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/26/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/26/2022 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 6/7/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/27/2022 | No Access for Inspection | HORACE FULTZ |
| Footing/Foundation/Slab | 6/27/2022 | No Access for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 6/27/2022 | No Access for Inspection | HORACE FULTZ |
| Wood Frame | 6/27/2022 | No Access for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 6/28/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/28/2022 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/28/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Wood Frame | 6/28/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 9/9/2022 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/7/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 10/7/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/17/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 10/17/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 10/17/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 10/24/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Final | 3/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 3/30/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 3/30/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/30/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/24/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/24/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/24/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/24/2023 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/24/2023 | Approved | ALIZAH MAYAGOITIA |