418 1/2 N ALFRED ST 90048

Certificate Information: 418 1/2 N ALFRED ST 90048

Application / Permit
21016-20000-27556
Plan Check / Job No.
B21VN12328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 25' 9" X 20' 2" STORAGE AND 19' 7" X 16' 9" CARPORT TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/6/2022
Issuing Office
Current Status
CofO Issued on 1/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 GURUNATH NESARAJAH
Corrections Issued 9/25/2021 GURUNATH NESARAJAH
Plan Check Approved 3/13/2022 GURUNATH NESARAJAH
Building Plans Picked Up 3/14/2022 APPLICANT
Issued 4/6/2022 APPLICANT
CofO in Progress 1/11/2024 LILIANA PORTILLO
Permit Finaled 1/14/2024 DEROLD HAUFF
CofO Issued 1/14/2024 DEROLD HAUFF
Permit Finaled 1/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/6/2021 CINDY QI
Sewer availability Cleared 12/6/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/9/2021 CINDY QI
Construction near power lines Cleared 2/27/2022 TINA MIRANDA
Construction within easement Cleared 2/27/2022 TINA MIRANDA

Contact Information

Contractor Adorn Construction; Lic. No.: 424795-B 19528 VENTURA BLVD #313      TARZANA, CA 91356

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Corrections Issued ADAM ESCOTO
Underground Mechanical 5/11/2022 Partial Approval ADAM ESCOTO
Sewer 6/10/2022 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 6/28/2022 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 8/22/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/15/2022 Corrections Issued MICHAEL LEWIS
Green Building Rough 9/15/2022 Approved MICHAEL LEWIS
HVAC-Rough 9/15/2022 Partial Approval MICHAEL LEWIS
METHANE-Rough 9/15/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 9/15/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/26/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/26/2022 Approved MICHAEL LEWIS
HVAC-Rough 9/26/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/4/2022 Approved MICHAEL LEWIS
Insulation 10/28/2022 Approved MICHAEL LEWIS
Drywall Nailing 11/15/2022 Approved JULIAN AMAYA
Interior/Exterior Lathing 11/18/2022 Approved MICHAEL LEWIS
Shower Pan 11/18/2022 Approved MICHAEL LEWIS
Drywall Nailing 11/28/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Inspection SCOTT FINNILA
Final 8/24/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 8/24/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV No Gas LILIANA PORTILLO
Smoke Detectors 8/24/2023 Approved LILIANA PORTILLO
Final 9/18/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 9/18/2023 Not Ready for Inspection LILIANA PORTILLO
Final 10/30/2023 Not Ready for Inspection JEFFREY MEAD
Green Building Final 10/30/2023 No Access for Inspection JEFFREY MEAD
Final 10/31/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 10/31/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/10/2024 Approved LILIANA PORTILLO
Final 1/10/2024 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 1/10/2024 Approved LILIANA PORTILLO
PLUMBING-Final 1/10/2024 Approved LILIANA PORTILLO
Service/Power Release 1/10/2024 Not Required LILIANA PORTILLO