11829-11831 N ELDRIDGE AVE 91342

Certificate Information: 11829-11831 N ELDRIDGE AVE 91342

Application / Permit
21016-20000-27554
Plan Check / Job No.
B21VN12327
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*ePlan Check* Convert existing attached 455 sf Garage to Accessory Dwelling Unit (ADU) PER GCS 65852.2(e)(1)(A) and PER WFPP
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
CofO Issued on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 MICHAEL LOPEZ
Corrections Issued 9/14/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 9/16/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 9/29/2021 MICHAEL LOPEZ
Applicant returned to address corrections 10/1/2021 MICHAEL LOPEZ
Plan Check Approved 10/6/2021 MICHAEL LOPEZ
Issued 10/12/2021 APPLICANT
CofO in Progress 3/23/2022 MICHEL ABAJAN
Permit Finaled 3/24/2022 RONALD MYRICK
CofO Issued 3/24/2022 RONALD MYRICK
Permit Finaled 3/24/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 9/15/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/15/2021 GABRIEL ROBLES
Sewer availability Cleared 9/15/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 9/21/2021 VASIL MIHALEV

Contact Information

Contractor Seven Seas Construction Services Inc; Lic. No.: 1065345-B 16350 VENTURA BLVD STE D527      LOS ANGELES, CA 91436

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/15/2021 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 10/20/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/9/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 11/9/2021 Approved MICHEL ABAJAN
Green Building Rough 11/9/2021 Approved MICHEL ABAJAN
HVAC-Rough 11/9/2021 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 11/9/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/16/2021 Approved MICHEL ABAJAN
HVAC-Rough 11/22/2021 Approved JESUS RODRIGUEZ
Insulation 11/22/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/22/2021 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 11/24/2021 Not Ready for Inspection JESUS RODRIGUEZ
Drywall Nailing 12/1/2021 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 12/1/2021 Corrections Issued GREGG CUMMINGS
Drywall Nailing 12/6/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 12/6/2021 Partial Inspection WILLIAM KUEHN
ELECTRICAL-Final 1/28/2022 Approved MICHEL ABAJAN
Final 1/28/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 1/28/2022 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 1/28/2022 Approved MICHEL ABAJAN
PLUMBING-Final 1/28/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/28/2022 Approved MICHEL ABAJAN
Final 3/23/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 3/23/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved MICHEL ABAJAN