8341 N CEDROS AVE 1-10 91402

Certificate Information: 8341 N CEDROS AVE 1-10 91402

Application / Permit
21016-20000-27539
Plan Check / Job No.
B21VN12316
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
*ePlan Check* CONVERT EXISTING ATTACHED GARAGE INTO TWO ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(C).
Permit Issued
Issued on 6/29/2023
Issuing Office
Current Status
Issued on 6/29/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/14/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 MICHAEL LOPEZ
Corrections Issued 10/21/2021 MICHAEL LOPEZ
Quality Review Completed 11/7/2021 HERNAN ARREOLA
Applicant returned to address corrections 12/10/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/8/2022 MICHAEL LOPEZ
Applicant returned to address corrections 12/20/2022 MINA HABIB
Applicant returned to address corrections 12/27/2022 MINA HABIB
Applicant returned to address corrections 5/1/2023 MICHAEL LOPEZ
Plan Check Approved 6/28/2023 MICHAEL LOPEZ
Issued 6/29/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/12/2021 AMIR KASHFI
Sewer availability Cleared 11/12/2021 AMIR KASHFI
Green Code Cleared 11/16/2021 AARON COSTA
Address approval Cleared 12/9/2021 AMIR KASHFI
Hydrant and Access approval Cleared 2/14/2022 DWAYNE LAURENT
Tenant Habitability Plan Cleared 11/17/2022 RICARDO BOHORQUEZ
DAS Clearance Cleared 1/11/2023 MINA HABIB
Miscellaneous Cleared 4/11/2023 MINA HABIB

Contact Information

Contractor One Structural Inc; Lic. No.: 1003868-B       ,
Contractor Retrofit 1; Lic. No.: 1003868-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: NA68149       ,

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2023 Approved ANDREW DORSO
Deputy Reinf. Concrete 8/2/2023 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 9/8/2023 Partial Inspection ANDREW DORSO
Green Building Rough 9/28/2023 Not Ready for Inspection ANDREW DORSO
Wood Frame 9/28/2023 Not Ready for Inspection ANDREW DORSO
Green Building Rough 11/21/2023 Approved KENNETH ROBERTS
Wood Frame 11/21/2023 Not Ready for Inspection KENNETH ROBERTS
Interior/Exterior Lathing 11/28/2023 Partial Inspection ANDREW DORSO
Wood Frame 5/14/2024 Approved ANDREW DORSO
Insulation 6/25/2024 Approved ANDREW DORSO
Drywall Nailing 7/9/2024 Approved ANDREW DORSO